RETROFITTING TO CORRECT UPLIFT OF CURVED GIRDER BRIDGE THROUGH FIELD TESTING AND ANALYSIS

Accession Number:

00820970

Record Type:

Component

Availability:

Transportation Research Board Business Office

500 Fifth Street, NW
Washington, DC 20001 United States

Find a library where document is available


Order URL: http://worldcat.org/isbn/0309072328

Abstract:

The Ramp C bridge at the New York State Thruway interchange with I-287 and New York State Route 17 in Rockland County near the New Jersey state line is a continuous four-span bridge with a reverse horizontal curve alignment. It consists of five steel girders with radial abutments and skewed pier supports (61 degrees). During construction immediately after the girders were erected and the counterweights were poured, at low temperatures, an unanticipated girder uplift occurred at one corner of an end span. Physical testing and analysis were undertaken to investigate this occurrence and to estimate the uplift forces. The data were used to design a tie-down system to correct the uplift problem and thus avoid delays in opening the bridge to traffic.

Supplemental Notes:

This paper appears in Transportation Research Record No. 1770, Design of Structures 2001.

Language:

English

Corporate Authors:

Transportation Research Board

500 Fifth Street, NW
Washington, DC 20001 United States

Authors:

Alampalli, S
Morreale, T A

Pagination:

p. 45-50

Publication Date:

2001

Serial:

Transportation Research Record

Issue Number: 1770
Publisher: Transportation Research Board
ISSN: 0361-1981

ISBN:

0309072328

Features:

Figures (4) ; Photos (5) ; References (2)

Geographic Terms:

Subject Areas:

Bridges and other structures; Design; Highways; I24: Design of Bridges and Retaining Walls