Abstract:
A HIGHWAY FILL WAS CONSTRUCTED ACROSS AN OPEN WATER COVE ON THE WEST SIDE OF SAN FRANCISCO BAY BY DISPLACING THE UNDERLYING SOFT MUD TO DEPTHS OF AS MUCH AS 60 FT. BY THE WEIGHT OF THE PLACED FILL. VARIOUS CONSTRUCTION METHODS WERE ATTEMPTED AND A METHOD OF OBTAINING REASONABLY UNIFORM MUD DISPLACEMENT DEVELOPED. THE FILL FAILURES WERE ANALYZED AND THE FACTORS AFFECTING THESE FAILURES EVALUATED. THE MEASURED SETTLEMENTS AND PORE PRESSURES ARE PRESENTED AND EVALUATED. THE PERFORMANCE OF THE HIGHWAY AFTER THREE YEARS OF USE IS GIVEN. /AUTHOR/
Supplemental Notes:
Vol 41, pp 591-610, 11 FIG, 4 PHOT. Distribution, posting, or copying of this PDF is strictly prohibited without written permission of the Transportation Research Board of the National Academy of Sciences. Unless otherwise indicated, all materials in this PDF are copyrighted by the National Academy of Sciences. Copyright © National Academy of Sciences. All rights reserved.